People-friendly remake of Avondale Estates’ main drag hits milestone
People-friendly remake of Avondale Estates’ main drag hits milestone
Josh Green
Thu, 06/05/2025 – 14:57
This week marks a year since the Complete Street overhaul of Avondale Estates’ primary traffic corridor broke ground, and city officials report that all aspects of the project are so far going according to plan.
Years in the making, the Complete Street remake of U.S. Highway 278 (North Avondale Road/East College Avenue) is designed to turn Avondale’s main drag into a more attractive, efficient, accessible, and safer corridor for drivers, cyclists, and pedestrians.
The project remains on schedule and budget, and it recently reached a “big milestone” by completing all stormwater pipe installation and underground utility relocation along the corridor, according to Avondale Estates spokesperson Ellen Powell.
Another new addition is decorative pavers in Avondale’s Tudor Village meant to echo the area’s architecture and expand outdoor seating options.
The most recent, updated overview of Complete Streets progress along U.S. Highway 278 (North Avondale Road/East College Avenue). Courtesy of Avondale Estates
The project is remaking a five-lane highway and basic sidewalk that pass the Town Green and many of Avondale Estates’ most popular restaurants and shops, reducing the roadway to three lanes for roughly 1.15 miles.
At the western end, the Complete Street will start at Sams Crossing near MARTA’s Avondale station; from there, it will travel past the new park and through downtown, ending at Ashton Place.
Changes in between call for a 10-foot-wide path for pedestrians and bicyclists, upgraded traffic signals, a center median, landscape buffer, pedestrian and bike crossings, as well as road repaving and re-striping.
According to Powell, Complete Street hardscape installation is continuing, including work on the multimodal path in places along the corridor. Once that’s wrapped, landscaping and signal installation will come this autumn, per Powell.
Recently completed aspects of the project include new pavers in Avondale’s Tudor Village that aim to reflect the distinctive architecture. Also shown is new seating in front of Galette bakery and a fresh Avon Theater marquee that returns the sign to its historic structure.Courtesy of Ellen Powell/Avondale Estates
City documents pertaining to the project stipulate the winning bidder was required to complete construction within 18 months.
Powell said this week the project is on pace to finish sometime in January next year.
In conjunction with the Town Green and a growing slate of retail and event spaces, the Complete Street project aims to create a more walkable, bikeable, and cohesive downtown for the DeKalb County city.
How a remade U.S. Highway 278 (North Avondale Road/East College Avenue) is expected to look and function through Avondale Estates’ downtown area. Courtesy of Avondale Estates
…
Follow us on social media:
Twitter / Facebook/and now: Instagram
• Avondale Estates news, discussion (Urbanize Atlanta)
Recently completed aspects of the project include new pavers in Avondale’s Tudor Village that aim to reflect the distinctive architecture. Also shown is new seating in front of Galette bakery and a fresh Avon Theater marquee that returns the sign to its historic structure.Courtesy of Ellen Powell/Avondale Estates

People-friendly remake of Avondale Estates’ main drag hits milestone
Josh Green
Thu, 06/05/2025 – 14:57
This week marks a year since the Complete Street overhaul of Avondale Estates’ primary traffic corridor broke ground, and city officials report that all aspects of the project are so far going according to plan. Years in the making, the Complete Street remake of U.S. Highway 278 (North Avondale Road/East College Avenue) is designed to turn Avondale’s main drag into a more attractive, efficient, accessible, and safer corridor for drivers, cyclists, and pedestrians.The project remains on schedule and budget, and it recently reached a “big milestone” by completing all stormwater pipe installation and underground utility relocation along the corridor, according to Avondale Estates spokesperson Ellen Powell. Another new addition is decorative pavers in Avondale’s Tudor Village meant to echo the area’s architecture and expand outdoor seating options.
Ongoing infrastructure work along North Avondale Road this week. Josh Green/Urbanize Atlanta
The most recent, updated overview of Complete Streets progress along U.S. Highway 278 (North Avondale Road/East College Avenue). Courtesy of Avondale Estates
The project is remaking a five-lane highway and basic sidewalk that pass the Town Green and many of Avondale Estates’ most popular restaurants and shops, reducing the roadway to three lanes for roughly 1.15 miles.At the western end, the Complete Street will start at Sams Crossing near MARTA’s Avondale station; from there, it will travel past the new park and through downtown, ending at Ashton Place.Changes in between call for a 10-foot-wide path for pedestrians and bicyclists, upgraded traffic signals, a center median, landscape buffer, pedestrian and bike crossings, as well as road repaving and re-striping. According to Powell, Complete Street hardscape installation is continuing, including work on the multimodal path in places along the corridor. Once that’s wrapped, landscaping and signal installation will come this autumn, per Powell.
Recently completed aspects of the project include new pavers in Avondale’s Tudor Village that aim to reflect the distinctive architecture. Also shown is new seating in front of Galette bakery and a fresh Avon Theater marquee that returns the sign to its historic structure.Courtesy of Ellen Powell/Avondale Estates
Construction this week near My Parents’ Basement restaurant. Josh Green/Urbanize Atlanta
City documents pertaining to the project stipulate the winning bidder was required to complete construction within 18 months.Powell said this week the project is on pace to finish sometime in January next year. In conjunction with the Town Green and a growing slate of retail and event spaces, the Complete Street project aims to create a more walkable, bikeable, and cohesive downtown for the DeKalb County city.
The roadway and narrow sidewalk in question today. Courtesy of Avondale Estates
How a remade U.S. Highway 278 (North Avondale Road/East College Avenue) is expected to look and function through Avondale Estates’ downtown area. Courtesy of Avondale Estates
…Follow us on social media: Twitter / Facebook/and now: Instagram • Avondale Estates news, discussion (Urbanize Atlanta)
Tags
City of Urban Redevelopment Agency Revenue Bonds Series 2023
Complete Streets
Alternate Transportation
DeKalb County
North Avondale Road
Town Green
Avondale MARTA Station
Moody’s
Standard & Poor’s
The Dale
Images
The most recent, updated overview of Complete Streets progress along U.S. Highway 278 (North Avondale Road/East College Avenue). Courtesy of Avondale Estates
Recently completed aspects of the project include new pavers in Avondale’s Tudor Village that aim to reflect the distinctive architecture. Also shown is new seating in front of Galette bakery and a fresh Avon Theater marquee that returns the sign to its historic structure.Courtesy of Ellen Powell/Avondale Estates
Ongoing infrastructure work along North Avondale Road this week. Josh Green/Urbanize Atlanta
Construction this week near My Parents’ Basement restaurant. Josh Green/Urbanize Atlanta
Josh Green/Urbanize Atlanta
Site work prepping for installation of a 10-foot-wide multimodal path as part of the Complete Street overhaul. Josh Green/Urbanize Atlanta
Facing west toward downtown Decatur, where construction work currently ends near Maple Street. Josh Green/Urbanize Atlanta
Extent of the Complete Street project stretching from Sams Crossing, at left, to Ashton Place in Avondale Estates. Google Maps
The roadway and narrow sidewalk in question today. Courtesy of Avondale Estates
How a remade U.S. Highway 278 (North Avondale Road/East College Avenue) is expected to look and function through Avondale Estates’ downtown area. Courtesy of Avondale Estates
Subtitle
Complete Street overhaul of North Avondale Road/East College Avenue broke ground a year ago
Neighborhood
Avondale Estates
Background Image
Image
Before/After Images
Sponsored Post
Off Read More