A true highlight of Atlanta’s growing web of multi-use trails is set to make its official debut soon. 

Livable Buckhead has scheduled a grand-opening celebration and ribbon-cutting from 4 to 7 p.m. Friday, Sept. 26 for the newest section of PATH400, a multi-modal cousin of the Atlanta Beltline that will link Buckhead to Sandy Springs. 

The one-mile segment, stretching between Wieuca Road up to Loridans Drive, includes the soaring Mountain Way Common bridge. 

That structure stands nearly 60 feet over the Mountain Way Common greenspace, between Ga. Highway 400 and towering trees. (Safety measures installed last year included taller and sturdier handrails along the bridge than initially planned. Phew!)


Guardrails being made studier than earlier plans had called for, as seen in fall 2024. PATH400; via Livable Buckhead


An “exit ramp” beneath the bridge that serves as a connection to Mountain Way Common, a greenspace along Nancy Creek, as shown in fall 2024. PATH400; via Livable Buckhead

Construction on the segment has spanned nearly two years, as complications arose related to unexpected protection measures for a bat wildlife habitat near the trail. The latest segment also included more than three total miles of walls, Livable Buckhead officials have said. 

North of the new bridge, the final unfinished PATH400 segment between Loridans Drive and the city limits of Atlanta/Sandy Springs is also under construction now. 

Beyond that, heading north, a 2.3-mile extension that would bring the Sandy Springs pathway up to the Interstate 285 and Ga. Highway 400 interchange is now fully funded with an $18 million grant from Atlanta Regional Commission. 


The Mountain Way Common bridge built by C.W. Matthews Contracting Company, as seen last fall. PATH400; via Livable Buckhead


Scope of finished PATH400 sections today and the northernmost section nearing completion now. Livable Buckhead/PATH400

Follow us on social media: 

Twitter / Facebook/and now: Instagram  

• Buckhead news, discussion (Urbanize Atlanta) 

Subtitle
Structure stands nearly 60 feet over the Mountain Way Common greenspace
Neighborhood
Background Image
Image
A photo showing a huge steel and concrete bike bridge next to yellow and red trees under blue skies in Buckhead Atlanta.
Before/After Images
Sponsored Post
Off

In Buckhead, opening set for PATH400 trail section with soaring bridge

Josh Green

Fri, 08/22/2025 – 14:14

A true highlight of Atlanta’s growing web of multi-use trails is set to make its official debut soon. Livable Buckhead has scheduled a grand-opening celebration and ribbon-cutting from 4 to 7 p.m. Friday, Sept. 26 for the newest section of PATH400, a multi-modal cousin of the Atlanta Beltline that will link Buckhead to Sandy Springs. The one-mile segment, stretching between Wieuca Road up to Loridans Drive, includes the soaring Mountain Way Common bridge. That structure stands nearly 60 feet over the Mountain Way Common greenspace, between Ga. Highway 400 and towering trees. (Safety measures installed last year included taller and sturdier handrails along the bridge than initially planned. Phew!)

Guardrails being made studier than earlier plans had called for, as seen in fall 2024. PATH400; via Livable Buckhead

An “exit ramp” beneath the bridge that serves as a connection to Mountain Way Common, a greenspace along Nancy Creek, as shown in fall 2024. PATH400; via Livable Buckhead

Construction on the segment has spanned nearly two years, as complications arose related to unexpected protection measures for a bat wildlife habitat near the trail. The latest segment also included more than three total miles of walls, Livable Buckhead officials have said. North of the new bridge, the final unfinished PATH400 segment between Loridans Drive and the city limits of Atlanta/Sandy Springs is also under construction now. Beyond that, heading north, a 2.3-mile extension that would bring the Sandy Springs pathway up to the Interstate 285 and Ga. Highway 400 interchange is now fully funded with an $18 million grant from Atlanta Regional Commission. 

The Mountain Way Common bridge built by C.W. Matthews Contracting Company, as seen last fall. PATH400; via Livable Buckhead

Scope of finished PATH400 sections today and the northernmost section nearing completion now. Livable Buckhead/PATH400

…Follow us on social media: Twitter / Facebook/and now: Instagram  • Buckhead news, discussion (Urbanize Atlanta) 

Tags

PATH400
Buckhead Trail
Alternate Transportation
Alternative Transportation
Atlanta Trails
Atlanta Bike Infrastructure
Atlanta Bike Paths
Atlanta Biking
Pedestrian infrastructure
Peachtree Creek Greenway
South Fork Conservancy
Mountain Way Common
Mountain Way Common bridge
GoBuckheadATL
C.W. Matthews
C.W. Matthews Contracting Co.
Glorified Sidewalk

Subtitle
Structure stands nearly 60 feet over the Mountain Way Common greenspace

Neighborhood
Buckhead

Background Image

Image

Before/After Images

Sponsored Post
Off  Read More 

cre101_93oscz